Final Completion Schedule!

 

We got our final schedule for completion for the house from our contractor! Yay!!!!  

3/31: 

  • Delivery of the 2 bathroom vanities and glass doors for both shower units
  • Start cathedral ceilings / bathroom ceilings +walls pine 

4/1: 

  • Glass company installing shower/ tub doors
  • Continue installing pine interiors

4/2-4/4: 

  • Interior finishes install

 

4/7-4/11: 

  • Interior finishes install / polyurethaning starts
  • Cabinets delivered/ installed
  • Electrician returns and installs remaining devices/ fixtures

4/14-4/18: 

  • Countertops templating
  • Interior finishes install / complete polyurethaning

4/21-4/25: 

  • Counters installed
  • Flooring install maybe 
  • Site guy to do driveway/ touch up site (maybe set generator)
  • Plumber finishes installing fixtures

4/28-5/2:

  • Final interior trims/ mouldings (after flooring
  • Walkthrough for interior punch list         

5/5-5/9: 

  • Finish up exterior work (deck rails, steps, etc)

5/12-5/16: 

  • Final punch list / walkthrough
  • Prep for final inspection (Certificate of Occupancy) 

 

5/19- 5/23: 

  • MOVE IN WEEK!!!!!  JUST IN TIME FOR SUMMER!!!!!!!!! 👍👍👍👍👍👍😃😃😃😃😃😃😃😃😃👏👏👏👏👏👏👏👏👏👏👏

 

 



Comments

  1. How exciting! And from the looks of things, you will sell very quickly too! This is going to run very smoothly for the two of you! I am so thrilled for you and can't wait for the next couple of blogs, as you approach your move-in date!!!

    ReplyDelete

Post a Comment

Popular posts from this blog

Catching Up: Wildlife

Latest Photos!

Weekend Visit!