Final Completion Schedule!
We got our final schedule for completion for the house from our contractor! Yay!!!!
3/31:
- Delivery of the 2 bathroom vanities and glass doors for both shower units
- Start cathedral ceilings / bathroom ceilings +walls pine
4/1:
- Glass company installing shower/ tub doors
- Continue installing pine interiors
4/2-4/4:
- Interior finishes install
4/7-4/11:
- Interior finishes install / polyurethaning starts
- Cabinets delivered/ installed
- Electrician returns and installs remaining devices/ fixtures
4/14-4/18:
- Countertops templating
- Interior finishes install / complete polyurethaning
4/21-4/25:
- Counters installed
- Flooring install maybe
- Site guy to do driveway/ touch up site (maybe set generator)
- Plumber finishes installing fixtures
4/28-5/2:
- Final interior trims/ mouldings (after flooring
- Walkthrough for interior punch list
5/5-5/9:
- Finish up exterior work (deck rails, steps, etc)
5/12-5/16:
- Final punch list / walkthrough
- Prep for final inspection (Certificate of Occupancy)
5/19- 5/23:
- MOVE IN WEEK!!!!! JUST IN TIME FOR SUMMER!!!!!!!!! 👍👍👍👍👍👍😃😃😃😃😃😃😃😃😃👏👏👏👏👏👏👏👏👏👏👏